Skip to main content

From 1 April 2024, the responsibility for LEP functions across the Enterprise M3 LEP region has transferred to Hampshire County Council and Surrey County Council.

The Enterprise M3 Board met for the last time in March 2024 and Enterprise M3 LEP is no longer operating as an organisation.

For any enquiries relating to economic development across the counties of Hampshire and Surrey, please visit the Hampshire County Council website and Business Surrey respectively.

Please note that Enterprise M3 LEP staff have transferred to Hampshire County Council to continue to deliver services and activities in Hampshire, including the Growth Hub, the Careers Hub, work on key business sectors, and trade and investment.  
They can be contacted at economic.development@hants.gov.uk.

Investment

Basingstoke North East Corridor to Growth - Phase 1 (A33 Popley Way junction and A33/A339 Ringway junction improvements)

Last updated 06 September 2019
bookmark Add to bookmarks
Basingstoke North East Corridor Growth

Project description

This scheme comprises a roundabout and a signal controlled junction in close proximity on the southern end of the A33, A33/A339 Ringway Roundabout and A33 Popley Way Junction. These junction improvements, along with future proposals along the A33 corridor, help address existing problems of journey time unreliability along the A33 and around Basingstoke, thus supporting access to jobs. In addition to increasing capacity and improving traffic flow, these works also improve access to proposed local development North of Popley Fields, Razors Farm, Cafaude Farm and Redlands and existing local business parks. A33 Reading Road / A339 Ringway Junction:

  • Construct an additional queuing lane on the A33 approach to the junction
  • Additional lane on the northern section of the gyratory
  • Updating the existing traffic signals Popley Way / A33 Junction:
  • Additional left turn slip lane at the Popley Way junction with the A33
  • Updated pedestrian and cycle crossing facilities
  • Updated signals at the junction

Project output

Part of the Basingstoke North Corridor to Growth package of projects. Taken together these will create a net increase of 264 jobs (plus an additional 102 construction jobs), 292 housing starts, and an additional £91m of Gross Value Added within the local economy.

Key Outputs

Start date:

End date:

Amount financed: £2.16 million

Total cost: £2.33 million

Status: Completed

Project Lead: Kevin Travers

Themes: Places

Geo-location: